planned-disbursement

iati-activities/iati-activity/planned-disbursement

This is the reference page for the XML element planned-disbursement. See also the relevant overview page: Budgets

Definition

The planned disbursement element should only be used to report specific planned cash transfers. These should be reported for a specific date or a meaningfully predictable period. These transactions should be reported in addition to budgets - which are typically annual breakdowns of the total activity commitment.

Rules

This element may occur any number of times.

Attributes

@type

Whether this is an original plan (prepared when the original commitment was made) or has subsequently been revised.

This value must be of type xsd:string.

This value must be on the BudgetType codelist.

Example Usage

Example planned-disbursement for an iati-activity.

This element is a parent for other child elements.
The @type attribute declares a valid code (1) from the BudgetType codelist.
<planned-disbursement type="1">
...
</planned-disbursement>
Note: If omitted, then BudgetType code 1 (Original) is assumed.
Full example with all child elements:
  <planned-disbursement type="1">
   <period-start iso-date="2014-01-01" />
   <period-end iso-date="2014-12-31" />
   <value currency="EUR" value-date="2014-01-01">3000</value>
  </planned-disbursement>
Note: multiple planned disbursements are expressed by repeating the planned-disbursement element.

Changelog

2.01

The attribute @last-updated was removed.

The attribute @type was added.

1.05

A description was added to this element

Developer tools

Find the source of this documentation on github: